The project involved a Landlord CAT A refurbishment of a 7,300 sq.ft first-floor office suite, including communal area upgrades, with works undertaken in a live building occupied by a ground-floor tenant.
Delivering high-quality results within a tight 10-week programme required precise coordination and planning to minimise disruption while adhering to a detailed scope of works that included internal and external improvements.
Our team worked closely with the client's consultant HTC, and other stakeholders to ensure seamless delivery of the programme.
By prioritising proactive communication and careful planning, we successfully coordinated works around the live environment and operational tenants to maintain progress while minimising disruption.
Roof repairs and replacement of louvres
Decorations to fixtures, fire escapes, and joinery
Replacement of external lighting
Overhaul of windows and landscaping, including car park yield-up
Refurbishment of the communal stairwell, including bespoke timber wall panelling, ceiling baffles, decorations, and upgraded floor coverings
Installation of new LED lighting
Refurbishment of dedicated W.C.s and shower facilities with new sanitaryware, IPS panels, tiling, and fixtures
Upgraded breakout area with new metal frame (MF) ceiling, flush inset LED lighting, large kitchen, and Amtico flooring
Office upgrades included energy-efficient LED lighting with passive infrared (PIR) sensors, ceiling tile replacements, and redecoration throughout. The existing carpet was retained, and mechanical ventilation with heat recovery (MVHR) units were serviced and repaired.
The project was completed on time and within budget in October 2022. The refurbished office suite and communal areas were handed over to the client, delivering a high-quality, energy-efficient space ready for tenant occupation.